Details:
PhilGEPS Reference No.: 9940381
Product/Service/Project Name:
1 lot Earthwork and Removal of Actual Structures /
Obstruction & Surface Restoration and Paving Works –
for the Proposed Installation of 8″Ø x 2,560M HDPE
Mainline Along San Carlos Heights, Irisan To Middle
Quezon Hill
Approved Budget: : ₱8,400,227.28 / lot
PO/NTP/Contract No.: 2506
Effectivity Date: November 23, 2023
Expiration Date: June 6, 2024
Delivery/Contract Period: 200 calendar days
Awardee/Supplier:Adroit Construction
Amount of Contract Awarded: ₱7,391,784.69 / lot
Date Posted: July 14, 2023